Question: Find the critical path and expected completion time (project duration) for the project. What is the effect on the project (critical path AND schedule duration)

- Find the critical path and expected completion time (project duration) for the project.
- What is the effect on the project (critical path AND schedule duration) if activity G takes an extra (is delayed) 3 weeks? If activity I is crashed (reduced) by 3 weeks?
Activity Predecessors Optimistic Duration Most likely Duration Pessimistic Duration A 7 10 19 B 6 10 14 C - 6 11 22 A, B 5 10 21 E A 7 15 17 F C 5 7 15 G B, C 8 9 16 H D, E 4 6 8 I E, F 6 J F, G 8 79 7 14 9 10
Step by Step Solution
There are 3 Steps involved in it
To solve this well apply the Program Evaluation and Review Technique PERT to calculate the expected durations and identify the critical path Step 1 Ca... View full answer