Find the discounted payback period for the following project. The discount rate 7%. Project X Initial Outlay
Fantastic news! We've Found the answer you've been seeking!
Question:
Find the discounted payback period for the following project. The discount rate 7%.
Project X
Initial Outlay $8,326
Year 1: $3,767
Year 2: $3,961
Year 3: $5,407
Year 4: $7,092
Round the answer to two decimal places.