Find the Earned Value, Cost Variance, Schedule Variance, Cost Performance Index and Schedule Performance Index of the
Fantastic news! We've Found the answer you've been seeking!
Question:
Find the Earned Value, Cost Variance, Schedule Variance, Cost Performance Index and Schedule Performance Index of the following task.
Activity | Start | Planned Duration | Actual Duration | Plan Date | Actual Date | Difference | Budget | Actual | Difference |
Call Center Stations | |||||||||
Call center stations inventory | 3/1/2020 | 14 | 14 | 3/15/2020 | 3/15/2020 | 0 | $2,100.00 | $2,100.00 | $0.00 |
Call center layout-new | 3/15/2020 | 15 | 18 | 3/30/2020 | 4/2/2020 | 3 | $ 4,500.00 | $ 5,400.00 | $900.00 |
Call center stations breakdown | 4/2/2020 | 8 | 13 | 4/10/2020 | 4/15/2020 | 5 | $ 2,400.00 | $ 3,900.00 | $1,500.00 |
Call center stations pack | 4/10/2020 | 5 | 20 | 4/15/2020 | 4/30/2020 | 15 | $ 1,500.00 | $ 6,000.00 | $4,500.00 |
Call center stations move | 4/30/2020 | 10 | 10 | 4/20/2020 | 5/10/2020 | 20 | $ 2,000.00 | $ 2,000.00 | $0.00 |
Call center stations install | 5/10/2020 | 9 | 15 | 5/1/2020 | 5/25/2020 | 24 | $1,800.00 | $3,000.00 | $1,200.00 |