Question: Find the Estimate at Completion ( EAC ) for this project.Budget at Completion ( BAC ) = 1 0 0 , 0 0 0 USD

Find the Estimate at Completion (EAC) for this project.Budget at Completion (BAC)=100,000 USD
Actual Cost (AC)=60,000 USD
Planned Value (PV)=50% of 100,000=50,000 USD
Earned Value (EV)=40% of 100,000=40,000 USD
To calculate the EAC, first you have to calculate the Cost Performance Index:
Cost Performance Index (CPI)= EV / AC =40,000/60,000=0.67
Estimate at Completion (EAC)= BAC/CPI =>100,000/0.67=149,253.73
Estimate at Completion (EAC) is 149,253.73 USD