Question: ) Find the project completion time for the following list of activities. Activit y Immediate Predecess or Duratio n A - 3 B - 3
) Find the project completion time for the following list of activities. Activit y Immediate Predecess or Duratio n A - 3 B - 3 C - 4 D A, B 5 E B, C 4 F D, E 2 G E 3 H F, G 5