Question: Find the project's total duration ( Critical path ) and date of completion ( assume the project start date is 1 3 ? 2 0

Find the project's total duration (Critical path)and date of completion (assume the project start date is 13?2022) Use the following derails to draw the A-O-N Network for the data in Table below
\table[[Activity,A,B,C,D,E,F,H,K,G,I,J,M],[\table[[Duration],[d]],4,5,6,8,3,7,11,4,8,9,4,6],[\table[[Following],[act.]],D,E,F,F,H,K,K,G,1,J,M,M,M,M,-]]
(30Marks)
 Find the project's total duration (Critical path)and date of completion (assume