Question: Find the project's total duration ( Critical path ) and date of completion ( assume the project start date is 1 3 ? 2 0
Find the project's total duration Critical pathand date of completion assume the project start date is Use the following derails to draw the Network for the data in Table below
tableActivityABCDEFHKGI,JMtableDurationdtableFollowingactDEFFHKKGMMMM
Marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
