Question: Find the schedule using graphical method to minimize the time needed to process the following jobs on the machines shown (i.e. for each machine,

Find the schedule using graphical method to minimize the time needed to process the following jobs on the machines shown (i.e. for each machine, find the job which should be scheduled first). Also, calculate the total time elapsed to complete both jobs. Job 1 Sequence ABCDE Time (Hrs). 43627 Job 2 Sequence CBEDA Time (Hrs) 63537
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts