Question: Find the sequence that will minimize make span ( time to complete all jobs) Calculate the average flow time. Calculate the average number of jobs

Find the sequence that will minimize make span (

  1. Find the sequence that will minimize make span ( time to complete all jobs)
  2. Calculate the average flow time.
  3. Calculate the average number of jobs in the system.
  4. If the due date for all jobs is at hour 30, determine the average lateness and average tardiness.
A manufacturer of sails for small boats has a group of custom sails awaiting the last two processing operations before the sails are sent to the customers. Operation 1 must be performed before operation 2, and the jobs have different time requirements for each operation. The hours required are as follows: Job 1 2 3 4 5 6 7 8 9 10 9 Operation 1 Operation 2 1 5 8 3 9 4 7 2 4 3 1 2 8 6 7 2 4 8 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!