Question: Finding inputs and outputs of a two - step function that models a real - work. 0 3 A construction crew needs to pave a

Finding inputs and outputs of a two-step function that models a real-work.
03
A construction crew needs to pave a road that is 209 miles long. The crew paves 7 miles of the road each day. The length, L(in miles), that is left to be paved after d days is given by the following function.
L(d)=209-7d
Answer the following questions.
(a) If 146 miles of the road is left to be paved, how many days has the crew been paving the road?
9 days
(b) How many miles of the road does the crew have left to pave after 11 days?
miles
 Finding inputs and outputs of a two-step function that models a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!