Question: Find:Job sequence, average flow time, average days late, average WIP: Priority Rule :SPT Priority Rule :EDD job Processing time( days) Due Date( days) a 10

  1. Find:Job sequence, average flow time, average days late, average WIP:
  2. Priority Rule :SPT
  3. Priority Rule :EDD

job Processing time( days) Due Date( days)
a 10 10
b 5 15
c 7 17
d 8 20
e 6 22
f 9 21
j 4 15