Question: Find:Job sequence, average flow time, average days late, average WIP: Priority Rule :SPT Priority Rule :EDD job Processing time( days) Due Date( days) a 10
- Find:Job sequence, average flow time, average days late, average WIP:
- Priority Rule :SPT
- Priority Rule :EDD
| job | Processing time( days) | Due Date( days) |
| a | 10 | 10 |
| b | 5 | 15 |
| c | 7 | 17 |
| d | 8 | 20 |
| e | 6 | 22 |
| f | 9 | 21 |
| j | 4 | 15 |