Question: Firm X is considering a project and its analysts have projected the following outcomes and their probabilities. OUTCOME PROBABILITY ASSUMPTIONS $5,250 25% Pessimistic $7,800 45%
Firm X is considering a project and its analysts have projected the following outcomes and their probabilities.
| OUTCOME | PROBABILITY | ASSUMPTIONS |
| $5,250 | 25% | Pessimistic |
| $7,800 | 45% | Moderately successful |
| $13,500 | 30% | optimistic |
What is the expected value of the outcomes?
A. $3,123
B. $8,460
C. $8,873
D. Cannot be determined/depends upon which prediction is correct