Question: firm's materials requirement is 5 0 , 0 0 0 units ( price Rs . 4 per unit ) . The ordering cost per order

firm's materials requirement is 50,000 units (price Rs.4 per unit). The ordering cost per order is Rs.20 and the carrying cost is 12.5%. If the discount schedule given below applies to the firm, determine the most economical order quantity.Discount RateLot Sizenone1-9991%1000-19992%2.000-2,9993%