Question: First : [4] Four projects are under consideration by an Engineering company. All projects have a 10-year life and the company's MARR is 7%. Details
![First : [4] Four projects are under consideration by an Engineering](https://dsd5zvtm8ll6.cloudfront.net/si.experts.images/questions/2024/09/66f85a338ccb5_05166f85a3325fa4.jpg)
First : [4] Four projects are under consideration by an Engineering company. All projects have a 10-year life and the company's MARR is 7%. Details about these projects as follows; The Net present worth (NPW) of project A is $3,429 The B/C ratio of project B is 0.98 The AW of project C is $554 The Internal rate of return (IRR) of project D = 6.85%. Which project should be selected? Explain your