Question: Five jobs are pending for a process that involves two sequential work centers. Using Johnson's Rule, determine the dispatching sequence. Job Work Center 1 Time
Five jobs are pending for a process that involves two sequential work centers. Using Johnson's Rule, determine the dispatching sequence.
| Job | Work Center 1 Time | Work Center 2 Time |
| A | 5 | 2 |
| B | 3 | 6 |
| C | 10 | 13 |
| D | 8 | 4 |
| E | 7 | 11 |
Load Sequence: