Five jobs are ready for processing at time zero through a workstation. The details of the processing
Fantastic news! We've Found the answer you've been seeking!
Question:
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
Job | Processing Time (days) | Due Date (days) |
A | 14 | 21 |
B | 7 | 10 |
C | 2 | 3 |
D | 3 | 6 |
E | 9 | 24 |
Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is?