Question: Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is

Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.

Job

Processing Time (days)

Due Date (days)

A

14

21

B

7

10

C

2

3

D

3

6

E

9

24


Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is?

Step by Step Solution

3.28 Rating (145 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The shortest processing time SPT rule is a scheduling rule that orders jobs in the ... View full answer