Question: Five jobs are required to be completed in a two - machine flow shop and their respective needed times are shown in the next table.
Five jobs are required to be completed in a twomachine flow shop and their respective needed times are
shown in the next table. Each job must begin with machine A and finish with machine B
Time minutes
Job Machine A Machine B
a Determine the sequence that will minimize the makespan.
b Construct a load Gantt chart for the resulting sequence and find machine As idle time.
c For the sequence determined in part a can machine As idle time be reduced by splitting some jobs
in half? If so which jobs?
d Split jobs and and draw the new load Gantt chart.