Question: Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's rule, what is the optimum sequence of jobs? Job Alpha Beta RSTU > 20 10 25 35 50 20 15 35 55 75 V-T-S-U-R; 225 U-R-T-S-V; 175 R-U-T-S-V; 175 U-S-V-T-R; 200 R-S-T-U-V; 240
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
