Question: Five jobs need to be done on a certain machine. However, the setup time for each job depends upon which job immediately preceded it ,
Five jobs need to be done on a certain machine. However, the setup time for each job
depends upon which job immediately preceded it as shown in the following table:
a Design a branchandbound algorithm for sequencing problems of this job by specifying how the branch, bound, and fathoming steps would be performed.
b Use this algorithm to solve this problem. that maximizes NPV using B&B