Five manufacturing orders are currently on a dispatch list and need to be run on an drilling
Fantastic news! We've Found the answer you've been seeking!
Question:
Five manufacturing orders are currently on a dispatch list and need to be run on an drilling machine. The number of units, run times per unit and the set-up time per each M.O. are given in the following table.
M.O. | Set-up (hr) | Number of units | Run time/unit (hr) |
A | 1 | 100 | .04 |
B | 1 | 100 | .01 |
C | 1 | 100 | .02 |
D | 1 | 100 | .03 |
E | 1 | 100 | .05 |
Create a schedule for these M.O.s to minimize the average flow times through this work center. Compute and report TET, mean-F and mean-Q times.