Question: fixed overhead standard - 2hrs per unit fixed overhead standard - $6 per hr variable overhead standard - 2hrs per unit variable overhead standard -
fixed overhead standard - 2hrs per unit
fixed overhead standard - $6 per hr
variable overhead standard - 2hrs per unit
variable overhead standard - $12 per hr
fixed overhead - $68,000
variable overhead - $101,000
actual units manufactured - 5,100 units



Tableau DA 8-3: Mini-Case, Compute direct labor and overhead variances LO P3, P4 Songsu Company is struggling to control costs. We are hired as consultants to determine why the company's actual costs exceed budgeted costs. The Tableau 1. \& 2. Compute the direct labor rate variance and direct labor efficiency variance. Indicate whether this cost variance is favorable, unfavorable or no variance. 3. Compute the total overhead variance. Indicate whether this cost variance is favorable or unfavorable. Complete this question by entering your answers in the tabs below. Compute the total overhead variance. Indicate whether this cost variance is favorable or unfavorable
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts