Question: Flooding would be devastating to the project; however, it is very unlikely. The project manager is most likely to __________ this risk. 1. prepare for
Flooding would be devastating to the project; however, it is very unlikely. The project manager is most likely to __________ this risk.
1. prepare for
2. acknowledge
3. distribute
4. retain