Question: Following are three independent projects Peanut/Pecan Processing (PPP) is evaluating: Project IRR Risk P 10.5 % Low Q 12.5 Average R 16.0 High PPP generally
Following are three independent projects Peanut/Pecan Processing (PPP) is evaluating:
| Project | IRR | Risk | |
| P | 10.5 | % | Low |
| Q | 12.5 | Average | |
| R | 16.0 | High |
PPP generally considers risk when examining projects by adjusting its average required rate of return, r, which equals 13 percent. A 4 percent adjustment is made for high-risk projects, and a 3 percent adjustment is made for low-risk projects. Which project(s) should PPP purchase? Round your answers to the nearest whole number.
| Project | Risk-Adjusted r | Acceptable? |
| P | % | |
| Q | % | |
| R | % |
Thus, what projects should be purchased.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
