Question: following Process Diagram for a five task line. Worker A 6 mins and Worker B 9 mins, Triangle, Worker C 12 mins, then split into

following Process Diagram for a five task line. Worker A 6 mins and Worker B 9 mins, Triangle, Worker C 12 mins, then split into 2 Worker D 15 mins, Then triangle, and Worker E 9 mins What is this line's capacity in an eight-hour day? Question 25 options: a) 53 units b) 80 units c) 40 units d) 32 units