Question: following table: table [ [ , table [ [ Normal ] , [ Time ( weeks ) ] ] , table [

following table:
\table[[,\table[[Normal],[Time (weeks)]],\table[[Crash],[Time (weeks)]],\table[[Normal],[Cost]],\table[[Total Cost],[with],[Crashing]],Immediate Predecessor(s)],[Activity,2,$1,200,$1,850,-,],[A,3,1,$2,300,$3,050,-],[B,2,1,$300,$300,-],[C,1,3,$1,500,$1,800,A],[D,7,3,$900,$1,200,B],[E,6,1,$4,000,$5,000,C],[F,2,$2,$1,600,$2,100,D, E],[G,4,,,,]]
a) Based on the given information regarding the activities for the project, the project completion date =14 weeks.
b) To reduce the duration of the project to 10 weeks at the least cost, the following is the order of what needs to be followed while crashing the activities:
The first activity to crash is 1 by 2 weeks at a per week crashing cost of dollars.
Next, one should crash activity D and activity A, by 2 weeks for an additional total per week crashing cost of dollars. WHAT IS THE VALUE IN THE BLANK
 following table: \table[[,\table[[Normal],[Time (weeks)]],\table[[Crash],[Time (weeks)]],\table[[Normal],[Cost]],\table[[Total Cost],[with],[Crashing]],Immediate Predecessor(s)],[Activity,2,$1,200,$1,850,-,],[A,3,1,$2,300,$3,050,-],[B,2,1,$300,$300,-],[C,1,3,$1,500,$1,800,A],[D,7,3,$900,$1,200,B],[E,6,1,$4,000,$5,000,C],[F,2,$2,$1,600,$2,100,D, E],[G,4,,,,]] a) Based on

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!