Question: following table. What is the critical path? Task Dependency Duration Start None 0 A Start 3 B A 2 C B 2 D START 4

following table. What is the critical path? Task Dependency Duration Start None 0 A Start 3 B A 2 C B 2 D START 4 E D 1 F START 5 G F 7 H B, E 3 I C, G, H 4 Finish I 0 Group of answer choices Start-D-E-H-I-Finish Start-A-B-C-I-Finish Start-A-B-H-I-Finish Start-F-G-I-Finish