Question: For 131 consecutive days, a process engineer has measured the temperature of champagne bottles as they are made ready for serving. Each day, she took
| For 131 consecutive days, a process engineer has measured the temperature of champagne bottles as they are made ready for serving. Each day, she took a sample of 5 bottles. The average across all 655 bottles (131 days, 5 bottles per day) was 40 degrees Fahrenheit. The standard deviation across all bottles was 0.8 degrees. | ||
| (Round your intermediate calculations and final answer to 4 decimal places.) | ||
| When constructing an X-bar chart, what would be the upper control limit? | degrees Fahrenheit | |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock