Question: For a certain project, the net present value at a discount rate of 15% is OMR 30,600, and at a rate of 18% the net
For a certain project, the net present value at a discount rate of 15% is OMR 30,600, and at a rate of 18% the net present value is OMR - 10,300. What is the internal rate of return of the project?
a) 16.6%
b)16.5%
c) 15.7%
d) 17.2%