Question: For a company using a continuous review system weekly demand of a product is 200 with a standard deviation of 50. What would be the
For a company using a continuous review system weekly demand of a product is 200 with a standard deviation of 50. What would be the reorder point for this product under 90% service level if the lead time is 3 weeks?
less than 600
greater than 600 but less than 750
greater than 750 but less than 850
greater than 850