Question: For a CPM model, you are given the following data with time in weeks. Activity Immediate Predecessors Normal Time Normal Cost Crash Time Crash Cost

For a CPM model, you are given the following data with time in weeks.

Activity

Immediate Predecessors

Normal Time

Normal Cost

Crash Time

Crash Cost

A

--

9

3200

5

6000

B

--

7

1400

5

2400

C

A

6

1500

5

2000

D

B

5

2500

3

4000

E

A, B

4

1800

3

2800

F

D, E

3

1800

1

4800

What is the critical path and the project completion time using normal times and the project completion time?

Ltfen birini sein:

a. B - D -F , 16

b. B - E - F , 16

c. A-E-F , 16

d. None

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!