Question: For a CPM model, you are given the following data with time in weeks. Activity Immediate Predecessors Normal Time Normal Cost Crash Time Crash Cost
For a CPM model, you are given the following data with time in weeks.
| Activity | Immediate Predecessors | Normal Time | Normal Cost | Crash Time | Crash Cost |
| ||||||
|
| A | -- | 9 | 3200 | 5 | 6000 | ||||||
|
| B | -- | 7 | 1400 | 5 | 2400 | ||||||
|
| C | A | 6 | 1500 | 5 | 2000 | ||||||
|
| D | B | 5 | 2500 | 3 | 4000 | ||||||
|
| E | A, B | 4 | 1800 | 3 | 2800 | ||||||
|
| F | D, E | 3 | 1800 | 1 | 4800 | ||||||
What is the critical path and the project completion time using normal times and the project completion time?
Ltfen birini sein:
a. B - D -F , 16
b. B - E - F , 16
c. A-E-F , 16
d. None