Question: for a distribution center, the transit time is 1 week, and the order quantity js 200 units. Gross Requirements from week 1 through 5 are

for a distribution center, the transit time is 1 week, and the order quantity js 200 units. Gross Requirements from week 1 through 5 are 150, 125,125, 100, 150 respectively. There are 200 units in transit, and the distribution center has projected available of 75 units. The projected available for periods 2, 3 and 4 are?
a. 200, 75, 175
b. 125, 0, 100
c. 75, 175, 25
d. 0, 75, 175
e. 125, 0, 75