Question: For a final product the time - phased net requirements for four weeks are given in the table below. The setup costs are K =
For a final product the timephased net requirements for four weeks are given in the table below. The setup costs are K and the holding cost per unit and week are h The orders are released on a SilverMeal basis. Which of the following statements are correct?
Week
Timephased net requirements
Question Select one or more:
a
The planned order release in week is
b
The planned order released in week is
c
The planned order release in week is
d
None of these.
e
The planned order release in week is
f
The planned order release in week is