Question: For a given process, the raw processing time is 1 0 2 sec , the bottleneck cycle time is 2 0 sec / item ,
For a given process, the raw processing time is sec the bottleneck cycle time is secitem and the WIP is items. What is the expected leadtime LT in seconds?