Question: For a given project activity, the optimistic duration estimate is 6, the pessimistic duration estimate is 34 and the most likely duration estimate is 22.

For a given project activity, the optimistic duration estimate is 6, the pessimistic duration estimate is 34 and the most likely duration estimate is 22. As we dealt with this activity in finding our critical path, what would we use as an estimated duration for it?