Question: For a given project, the critical path length is 20 weeks. What will happen if we cut the critical path length by 4 weeks? Group
For a given project, the critical path length is 20 weeks. What will happen if we cut the critical path length by 4 weeks?
Group of answer choices
The project will be delayed by 4 weeks
The project can be completed in 16 weeks for sure
The project can be possibly finished in 16 weeks
The project still needs 20 weeks of completion time