Question: For a particular operation, the setup time is 1 0 minutes and the run time is 5 0 minutes to produce a standard lot of

For a particular operation, the setup time is 10 minutes and the run time is 50 minutes to produce a standard lot of 40 parts. It takes three additional hours to circulate a container of parts after production is completed. The demand rate is 20,000 parts per month. There are 160 production hours in a month.
a. How many standard containers are needed? (Round your answer up to the next integer.)
b. What is the takt time of this process? Process takt time in seconds.