Question: For a particular operation, the setup time is 1 0 minutes and the run time is 5 0 minutes to produce a standard lot of
For a particular operation, the setup time is minutes and the run time is minutes to produce a standard lot of parts. It takes three additional hours to circulate a container of parts after production is completed. The demand rate is parts per month. There are production hours in a month.
a How many standard containers are needed? Round your answer up to the next integer.
b What is the takt time of this process? Process takt time in seconds.