Question: For a process shown below, what is the Activity Efficiency (AE) for unprimed flow? Operation A Operation B Operation C Operation D C/T mins 2
For a process shown below, what is the Activity Efficiency (AE) for unprimed flow?
| Operation A | Operation B | Operation C | Operation D | |
| C/T mins | 2 | 4 | 8 | 6 |
| Shift time mins | 480 | |||
78.5%
73.3%
60.9%
69.7%