Question: For a process shown below, what is the lead time for completing a batch size given, if the products are moved from one operation to
For a process shown below, what is the lead time for completing a batch size given, if the products are moved from one operation to the other as a batch? Batch size C/T for C/T for C/T for / for pieces A in minsB in minsin mins Din mins 36 10 16 20 17 1008 minutes 2100 minutes 2268 minutes 2280 minutes