Question: For a process, the 12 th unit required 38 minutes, while the 6 th unit required 51 minutes. How much time would you predict the
For a process, the 12th unit required 38 minutes, while the 6th unit required 51 minutes. How much time would you predict the 18th unit required?
31.99 minutes
45.14 minutes
18.73 minutes
42.17 minutes
none of the above