Question: For a statistical process control chart design average run lenght (ARL) is calculated to be 80 days. Can we say that it is impossible to

  1. For a statistical process control chart design average run lenght (ARL) is calculated to be 80 days. Can we say that it is impossible to get out of control signal before 80 days after last out of control signal? Why?