Question: For all questions in this assignment, map this process: Task Predecessor Task Time (seconds) A -- 50 B A 30 C A 30 D B

  1. For all questions in this assignment, map this process:

    Task Predecessor Task Time (seconds)
    A -- 50
    B A 30
    C A 30
    D B 10
    E B,C 40
    F D 40
    G F 50
    H E 60
    I G,H 50

    If we have one worker at each station, and if everyone works at the speed listed in task time, what is the bottleneck?

    A

    B

    C

    D

    E

    F

    G

    H

    I

    ITS NOT A, I or D