Question: For all questions in this assignment, map this process: Task Predecessor Task Time (seconds) A -- 50 B A 30 C A 30 D B
-
For all questions in this assignment, map this process:
Task Predecessor Task Time (seconds) A -- 50 B A 30 C A 30 D B 10 E B,C 40 F D 40 G F 50 H E 60 I G,H 50 If we have one worker at each station, and if everyone works at the speed listed in task time, what is the bottleneck?
ITS NOT A, I or DA
B
C
D
E
F
G
H
I