Question: For competing projects, the selection process should be based on: Multiple Choice the highest IRR. the largest NPV. the longest life span. the smallest investment.

For competing projects, the selection process should be based on: Multiple Choice the highest IRR. the largest NPV. the longest life span. the smallest investment. the largest investment