Question: For computations, use Excel. For drawing, you can utilize Excel or Word. Refer to the Solved Problem example for some hints. Feel free to utilize
For computations, use Excel. For drawing, you can utilize Excel or Word. Refer to the Solved Problem example for some hints. Feel free to utilize Excel QM or QM for Windows. However, provide all the required information. Tom Marcus, a director of personnel at Management Resources, Inc., is in the process of designing a program that its customers can use in the job-finding process. Some of the activities include preparing resumes, writing letters, making appointments to see prospective employers, researching companies, and industries, and so on. Necessary information on the activities is shown in the following table:
| DAYS | |||||
| ACTIVITY | o (otimistic) | p (pessimistic) | m (most likely) | IMMEDIATE PREDECESSORS | |
| A | 4 | 6 | 5 | - | |
| B | 2 | 8 | 5 | - | |
| C | 5 | 9 | 7 | A | |
| D | 4 | 6 | 5 | A | |
| E | 2 | 6 | 4 | B | |
| F | 3 | 9 | 6 | B | |
| G | 10 | 12 | 11 | C, E | |
| H | 7 | 9 | 8 | D, F |
(e). Determine the probability that the project will be finished in 23 days or less. (f). Determine the probability the the project will NOT be finished in 26 days or less. (g). Determine the probability that the project will be finished in 25 days or less. (h). If a manager considers crashing any of the tasks to reduce the duration of the project completion time, which tasks should he/she focus on? Why?