Question: For each problem, determine lambda , mu , and S . 1 . Customers come with questions or complaints or matters regarding credit
For each problem, determine lambda mu and S
Customers come with questions or complaints or matters regarding creditcard bills. The customers are served by store representatives, each located in a partitioned stall. Customers are treated on a firstcome, firstserved basis. A study of the service department for months shows that an average interarrival time is minutes and an average of customers can be served per hour by a customer service representative
Activity Immediate
Predecessor Normal
Time Crash
Time Normal
Cost Crash
Cost
A $ $
B A $ $
C A $ $
D A $ $
E BCD $ $
F E $ $
What is the project completion time before it crashes? points
Which activity should crash first to reduce the completion time to one day? points
Suppose you crashed one day. If you want to crash another day after crashing one day,
which activity or activities should you crash? day, which activity or activities should
you crash? points
What is a the project completion time of the fully crashed project and b the total
additional cost of the fully crashed project? points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock