For Learning Curve analysis, if the first unit requires 10 total labor hours, and the next two units require only 18 hours total, which of the following is true?
A: This is a 90% learning curve
B: The improvement rate is 10%
C: The next 4 units should require approximately 32.4 hours total
D: All of the choices are true
E: None of the choices are true