Question: For most construction projects, Bradley Heating and Cooling buys sheet metal and forms the metal into heating /cooling ducts as needed. The company estimates the
For most construction projects, Bradley Heating and Cooling buys sheet metal and forms the metal into heating
/cooling ducts as needed. The company estimates the costs of making and installing ductwork for Kerry Park
shopping mall to be as follows:
Materials------------------------------------------------------$35,000
Labor to form ductwork------------------------------------3,000
Labor to install ductwork---------------------------------9,000
Misc. variable cost----------------------------------------1,500
Fixed costs allocated based on labor hours------3,000
Total costs--------------------------------------------------$51,500
The fixed costs relate to the companys building equipment, and office staff. The company plans on billing the
Kerry Park developer $68,000 for services. Bradley is currently behind schedule on other projects and is
paying a late penaalty of $1,200 per day. Walt Bradley, the owner of bradley heating and cooling, is considering
ordering prefabricated ductwork for the Kerry Park job. The prefabricated ductwork will cost $40,000 (including the
cost of sheet metal). If Walt buys the prefabricated ductwork, he'll be able to reassign workers to another project
and avoid 5 days of late fees.
REQUIRED: Answer Question And fill out chart below.
Should Bradley make the ductwork or buy it prefabricated?
FILL OUT THE CHART
Do not buy prefabricated Buy prefabricated Buy difference
Materials ? ? ?
Title? ? ? ?
Title? ? ? ?
Title? ? ? ?
Title? ? ? ?
Title? ? ? ?
Total Formula Formula Formula
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts