Question: For Option C: the only task options are: F E-G B E-D B B-C-E Please complete chart using these options. Please, Thank you! The desired

For Option C: the only task options are: F E-G B

For Option C: the only task options are:

F

E-G

B

E-D

B

B-C-E

Please complete chart using these options. Please, Thank you!

The desired daily output for an assembly line is 340 units. This assembly line will operate 425 minutes per day. The following table contains information on this product's task times and precedence relationships: IMMEDIATE PREDECESSOR TASK A B D E E G H TASK TIME (SECONDS) 30 35 30 35 15 65 40 25 A B E-F D-G b. What is the required workstation cycle time to meet the desired output rate? Workstation cycle time 75 seconds per unit c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. (Leave no cells blank - be certain to enter "0" wherever required.) Work Station Idle Time Task A-C-E 1 11 IV

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!