Question: For part a D is the correct answer. I need help answering part b a. Choose the correct network diagram below. OA . Q 5
For part a D is the correct answer. I need help answering part b
a. Choose the correct network diagram below. OA . Q 5 A-B-D-G-J A-C-F-I-J Q Q Q A-C-F-H- F a IS IS A-B-F-E-J A-B-F-H-J b. Calculate the chil A-B-E-GU t The critical path is A-B-DG-J and the project duration is days (Enter your response as a whole number)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
