Question: * (For problems 4 and 5) Activity Immediate Predecessor(s) Time (weeks) 3 5 4 MUWLUI- BBE B AC DF E 3 7 5 4. What

* (For problems 4 and 5) Activity Immediate

* (For problems 4 and 5) Activity Immediate Predecessor(s) Time (weeks) 3 5 4 MUWLUI- BBE B AC DF E 3 7 5 4. What is the earliest completion time for this project? A. 12 weeks B. 14 weeks C. 16 weeks D. none of the above 5. What is the largest amount of slack that any activity in the project has? A. 1 week B. 2 week C. 3 weeks D. 4 or more weeks