Question: For projects, not using earned value management, how to perform schedule variance analysis as part of the Schedule Control process? (1 Point) By comparing planned

For projects, not using earned value management, how to perform schedule variance analysis as part of the Schedule Control process?

(1 Point)

By comparing planned activity start or finish dates against actual start or finish dates to identify variances between the schedule baseline and actual project performance

By measuring the SV and SPI for the current progress

For projects not using earned value management, cannot have the schedule variance analyzed

None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!