Question: For projects, not using earned value management, how to perform schedule variance analysis as part of the Schedule Control process? (1 Point) By comparing planned
For projects, not using earned value management, how to perform schedule variance analysis as part of the Schedule Control process?
(1 Point)
By comparing planned activity start or finish dates against actual start or finish dates to identify variances between the schedule baseline and actual project performance
By measuring the SV and SPI for the current progress
For projects not using earned value management, cannot have the schedule variance analyzed
None of the above