Question: For several months, the development team for your project has been holding reviews at the end of each iteration. As the project manager, you are

For several months, the development team for your project has been holding reviews at the end of each iteration. As the project manager, you are pleased with their progress. However, you hear that the project sponsor has told another stakeholder that nothing is getting done using that agile approach. What should you do?
Group of answer choices
b. Ask the team to start showing working software that has business value rather than prototypes.
a. Educate the sponsor about agiles incremental approach.
c. Invite the sponsor to attend the teams next iteration review.
d. Ask the product owner to report the project performance to the sponsor.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!